The Red E team recently rebuilt a 40-foot John Deere 1890 drill with roughly 30,000 acres of use. The front rank needed the most help, as all of the depth adjusters were seized. The closing wheel arms were quite sloppy when we did our initial inspection, and those were changed out as well. We discovered corrosion and rust on the lower kit (Matt documented this on camera).

This project used four of our rebuild experts on the job site. We cover the process in a step-by-step guide and include a walkthrough video below.

Video

How to Remove STUCK Depth Adjuster Arms and Covers on John Deere 1890

Step-by-Step

Необходимое время: 2 дня

  1. Assessing the Equipment

    We begin by examining the 195-bushel cart and the drill itself. The rear tank was in good condition. However, the front tank showed significant corrosion, particularly on the end caps and lower kit.assessing 1890 drill

  2. Disconnecting the Front Tank

    We started by removing the bolts at the top plate and disconnecting the ladder. The goal was to drop the entire tank down to assess the extent of the damage and determine the necessary repairs.

  3. Beginning the Disassembly of the Drill Rows

    We began disassembling the front rank of the drill, noting that the depth adjusters were seized, and the closing alarms were sloppy. We identified one severely damaged roll unit on the rear rank, located near the fold pivot.disassembling drill row

  4. Removing Cover Plates and Handles

    Using an M12 ratchet impact, the nuts were removed from the cover plates. The cover plates, handles, and springs are then removed, and placed in trays to prevent lost fasteners. The depth adjuster arms are torched off.removing the cover plate

  5. Hub Maintenance

    We begin day two by working on the hubs and removing seals and wearings. The rolls are stripped bare, preparing them for reassembly.

  6. Seed Boot and C-Tab Replacement (Rear Rank)

    On the rear rank, we start replacing the seed boots, boot springs, and C-tabs. We highlighted the difference between worn boots and new Needham Ag boots and emphasized the improved thickness and durability of the new boots. The bolts are reinstalled with Loctite to prevent loosening.pointing to seed boot

  7. Bearing Assessment and Maintenance

    We assessed the bearings and decided to replace only the seals and wearings, as the bearings have significant life remaining. Usage and long-term plans with bearings are always a good discussion as well during this part of the process. assessing bearings on 1890

  8. Closing Wheel and Press Wheel Arm Installation

    The closing wheel and press wheel arms were installed. We ensured all components were properly aligned and secured.

Final Touches

The entire project was completed in two days, including installing arms and gauge wheels. We had the customer review our work while discussing the changes.